Variance of a network having several critical paths

In case of two critical paths, while calculating variance for project length, whether I am supposed to take total variance of all critical activities or we shall first calculate variance of all critical paths separately & then take highest variance as variance of project length.
shilpa is offline  
 
Reply

  My Math Forum > Science Forums > Economics

Tags
critical, network, paths, variance



Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Arrive specific place time with variance 0 u r neg variance BenFRayfield Complex Analysis 0 January 20th, 2014 05:42 AM
Number of paths from A to B texaslonghorn Elementary Math 9 April 22nd, 2013 05:21 PM
Paths from a to b on a complex plane Ryon Complex Analysis 1 June 2nd, 2010 05:32 AM
composition of paths pascal4542 Real Analysis 1 February 7th, 2009 07:06 PM
Shortest paths on a trumpet bill Real Analysis 0 September 12th, 2007 12:44 PM





Copyright © 2019 My Math Forum. All rights reserved.